Rowan Gorilla VII Jack Up Rig Upgrade

Stowen are pleased to be associated with the successful Rig Upgrade on the Gorilla VII for Rowan.

The Project

Project- Jack Up Rig Upgrade
Duration- 5 Months
Location- Dundee
Man Power- 80 Man Project and Construction Team

The Scope

  • Project Planning & Engineering
  • Installation of New BOP & Diverter Control System
  • Installation of New BOP Tension Jacks & Riser Tensioning System
  • Installation of New BOP & Annular Access Platforms
  • Installation of New NOV TDX1000 Guide Tracks
  • Replacement of Cyber Based Chairs with Amphion Control Chairs in New NOV Drillers Cabin
  • Installation of New NOV Drillers Cabin
  • Installation of New NOV VFD House
  • Installation of New NOV TDX1000 & Traveling Block
  • Installation of New TDX1000 Service Systems
  • Installation of New TDX1000 Cooling Skid
  • Installation of New Zone Management System
  • Installation of New Drilling Package CCTV System
  • Installation of New Choke & Kill Manifold Control System
  • Installation of New Drawworks Control System
  • Installation of New Mud Pump Control System
  • Installation of New Helideck Netting
  • Installation of New Frag Hangers
  • Installation of New Air Craft Warning Lights
  • Derrick, Guide Track & Rotary Table Alignment
  • LER & SCR Modifications
  • SCR Sea Water Piping Replacement
  • Leg Liner Replacement
  • Jetting Line Bolt Replacment
  • Jacking Column Repairs
  • Drill Floor Winch Repositioning
  • Crown Pad Eye Replacement
  • 18” Deflector Valve Replacement
  • HP Stand Pipe Modifications
  • Cantilever Extension Modifications & Installation
  • Kato Generator Removal
  • Redundant Steam Line Removal