Rowan Gorilla VI Jack Up Rig Upgrade
Stowen are pleased to be associated with the successful Rig Upgrade on the Gorilla VI for Rowan.
The Project
Project- Jack Up Rig Upgrade
Duration- 4 months
Location- Dundee/ Trinidad
Man 25 Man Construction Team
The Scope
- Crane cab relocation
- ST-120 realignment
- Dropped object deck removal
- Electrical ID tagging
- NDT of legs & leg repairs
- Screw conveyor replacement
- Trip tank reinforcement
- Crane boom rest extensions
- P-Tank piping modifications
- Replacement of mud pit valves
- Installation of new bulk dust collector system
- New mud trough fabrication supply & installation
- Replacement of cantilever hold down liners
- Cantilever strengthening
- Cantilever crack repairs
- Replacement of blast deflector valve
- Cantilever BOP piping modifications
- Shear line valves piping modifications
- Replacement of damaged electrical cables in cantilever festoon
- Jacking column repairs
- Quad HPU motor replacement
- Mud pump bleed off valve replacement
- Main engine exhaust stack modifications