Valaris Stavanger Jack up Rig Upgrade
Stowen are pleased to be associated with the Jack up Rig Upgrade on Stavanger for Valaris.
The Project
Project – Jack Up Rig Up Grade
Client – Valaris
Asset – Stavanger
Location – Dundee
Duration – 9 Weeks
Personnel – 12 Man Multi Skilled Construction Team
The Scope
- New NOV ST-120 Installation
- BOP Crane NDT Inspection
- Accommodation & Loading Area Bumper Bars Supply & Installation
- Main Engine Radiator Replacement
- Electrical Equipment Tagging
- MetOcean Instrumentation Installation
- 5” HP Cement Line Supply & Installation
- Moon Pool Roller Shutter Door Repositioning
- BOP Test Stump Supply & Installation
- HP Mud Line Modifications
- 2” Well Test Line Supply & Installation
- BOP Bulk Head Modifications
- Overboard Discharge Line Modifications
- Platform Interface Electrical Installation
- MPD Piping Modifications, Valve Installation & Pressure Testing
- Raw water Pump Replacment
- Transom Platform Grating Replacment
- Transome Pad Eyes Supply & Installation
- Installation of 3rd Party Interfaces
- New NOV ST-120 Installation
- Operations Punch List